NEW QUESTION # 137
Key performance indicators (KPIs) are used for measuring how a project is progressing towards success and are monitored by project managers:
- A. not more frequently than monthly.
- B. only when assessing project risk.
- C. at the post-project review.
- D. throughout the project.
Answer: D
NEW QUESTION # 138
Scheduling can best be defined as the process used to determine:
- A. project cost.
- B. sub-contractor's responsibilities
- C. the project management plan.
- D. overall project duration.
Answer: D
NEW QUESTION # 139
The characteristics of a product that determine whether it meets certain requirements is known as the:
- A. success criteria.
- B. product criteria.
- C. acceptance criteria.
- D. quality criteria.
Answer: C
NEW QUESTION # 140
What rule of thumb. can be used for ensuring that key stakeholders have been included in the process?
- A. Make use Of widely available templates and predefined structures to ensure a complete spectrum of stakeholders are identified.
- B. Question whose support or lack of it might significantly influence the success of the project
- C. Ask the most influential stakeholders to identify who else they think Should be involved in the project.
- D. Analyse Other projects and who their stakeholders are and include them by default.
Answer: B
NEW QUESTION # 141
Portfolio management includes prioritising:
- A. projects and/or programmes that contribute directly to the organisation's strategic objectives.
- B. projects with exceptionally high returns on investment.
- C. projects which maximise change over those which maximise investment
- D. projects and programmes over business as usual.
Answer: A
NEW QUESTION # 142
Who would be typically described as the person or organisation best placed to deal with a risk?
- A. Sponsor.
- B. Project sponsor.
- C. Risk owner.
- D. Risk manager.
Answer: C
NEW QUESTION # 143
A responsibility assignment matrix (RAM) allows the project manager to cross reference:
- A. the organisational breakdown structure (OBS) with the product breakdown structure (PBS) to assign resources to deliverables.
- B. the organisational breakdown structure (OBS) with the cost breakdown structure (CBS) to assign A. cost to each resource.
- C. the product breakdown structure (PBS) with the work breakdown structure (WBS) to assign activities to the products.
- D. the work breakdown structure (WBS) with the organisational breakdown structure (OBS) to match resources to the tasks.
Answer: D
NEW QUESTION # 144
Which is one of the three key project constraints?
- A. Technical
- B. Political
- C. Environmental
- D. Time
Answer: D
NEW QUESTION # 145
Which one of the following statements best describes a project?
- A. A project is a method of planning work.
- B. A unique transient endeavour undertaken to achieve a desired outcome.
- C. A project is the sum of activities needed to remove uncertainty from a unique piece of work.
- D. A project is a set of tools and techniques often used when delivering organisational change.
Answer: B
NEW QUESTION # 146
What aspects of benefits realisation would be considered as most important to note in the business case?
- A. How the benefits will be realised, measured and the stakeholders involved
- B. Who is going to be responsible for carrying out each of the projects activities.
- C. Which benefits should be realised first and then the subsequent order
- D. What type of contract is going to be used to procure delivery of the project.
Answer: A
NEW QUESTION # 147
Which one of the following best describes A. programme?
- A. A group of projects collected together because of their relationship to business-as-usual.
- B. A group of projects collected together that have a common purpose.
- C. A group of projects collected together for management convenience.
- D. A group of projects collected together because of their use of common resources.
Answer: B
NEW QUESTION # 148
What is one of the most important aspects to establish about a stakeholder's interest in the project?
- A. If it is positive or negative.
- B. If it is regular or intermittent.
- C. If it is influenced by other stakeholders.
- D. If it is influenced by the project.
Answer: A
NEW QUESTION # 149
What is meant by the term programme management?
- A. The line management of A. team of programme managers.
- B. The management of A. group of projects or activities that have a common business aim.
- C. The management of the programme of activities identified in the project plan
- D. The management of A. functional are aused by a number of different projects.
Answer: B
NEW QUESTION # 150
In which phase of the project should the Procurement Strategy be written?
- A. Definition
- B. Transition
- C. Deployment
- D. Concept
Answer: A
NEW QUESTION # 151
Which technique could be used by a project manager when resources are limited?
- A. Resource levelling.
- B. Resource expansion
- C. Resource estimation.
- D. Resource aggregation.
Answer: A
NEW QUESTION # 152
Which of the following statements describes a key difference between quality assurance and quality control?
- A. Quality control is about testing whilst quality assurance is about planning.
- B. Quality control is about management whilst quality assurance is about controlling change.
- C. Quality control is about fitness for purpose whilst quality assurance is about testing.
- D. Quality control is about fitness for purpose whilst quality assurance is about management confidence.
Answer: D
NEW QUESTION # 153
Establishing success criteria is important at the start of the project, as they:
- A. indicate what is important in supplier selection.
- B. indicate how the stakeholder needs will be met.
- C. ensure adequate resource allocation.
- D. ensure comprehensive risk analysis.
Answer: B
NEW QUESTION # 154
A project life cycle which combines approaches from the linear and iterative life cycles is known as _________ project life cycle.
- A. an extended.
- B. a hybrid.
- C. a reduced.
- D. a combined.
Answer: B
NEW QUESTION # 155
A project manager would use a cost breakdown structure to produce:
- A. high-level project costs.
- B. an analytical estimate.
- C. the cost of a do-nothing option.
- D. a comparative estimate.
Answer: B
NEW QUESTION # 156
Which one of the following statements best defines teamwork?
- A. Establishing vision and direction towards a common purpose.
- B. People working collaboratively towards a common goal.
- C. Gathering the right people together to work on a project.
- D. Developing skills that will enhance project performance.
Answer: B
NEW QUESTION # 157
Project reporting can best be defined as:
- A. gathering stakeholder feedback.
- B. informing stakeholders about the project.
- C. storing and archiving of project information.
- D. collecting project information.
Answer: B
NEW QUESTION # 158
Which of the following provides the project manager with a formal overview of project quality?
- A. Historical experience.
- B. Design reviews
- C. Quality audits.
- D. Project definition reports.
Answer: C
NEW QUESTION # 159
Which of these is not part of the linear project life cycle?
- A. Transition
- B. Definition
- C. Concept
- D. Operations
Answer: D