
SAP C-TS422-2601 Exam Questions (Updated 2026) 100% Real Question Answers
Pass SAP C-TS422-2601 Exam Quickly With Actual4dump
NEW QUESTION # 20
Which actions does the system perform by default when you save a confirmation for a finished product in repetitive manufacturing?
Note: There are 3 correct answers to this question.
- A. Post production costs to the planned order.
- B. Post the goods receipt for the finished product.
- C. Reduce run schedule quantities.
- D. Update statistics for the Business Information Warehouse.
- E. Create associated capacity requirements.
Answer: A,C,E
NEW QUESTION # 21
What time element of midpoint scheduled operations can be reduced by reduction strategy settings while dispatching?
Note: There are 2 correct answers to this question.
- A. Queue time
- B. Teardown time
- C. Setup time
- D. Move time
Answer: A,D
NEW QUESTION # 22
What are the key features of using a low level code?
Note: There are 2 correct answers to this question.
- A. To determine how costs are rolled up by product costing
- B. To determine the use of subitems inside material BOM (bill of material)
- C. To determine the priority of alternative components inside ATP
- D. To determine the sequence in which materials are planned in MRP
Answer: A,D
NEW QUESTION # 23
What could be the reason for different combinations of components in a multiple bill of material (BOM)?
Note: There are 2 correct answers to this question.
- A. BOM header status
- B. Manufacturing date
- C. BOM component status
- D. Lot size
Answer: B,D
NEW QUESTION # 24
When does the system trigger replenishment for a Kanban container?
- A. When you set the container to Empty
- B. When you set the container to In transit
- C. When you set the container to Waiting
- D. When you set the container to Full
Answer: A
NEW QUESTION # 25
What will happen in the MRP run if you have created a new MRPrelevant material that supports both inhouse production external procurement?
- A. The MRP run assumes external procurement.
- B. The MRP run does NOT consider the material; it has to be planned interactively.
- C. The MRP run assumes inhouse production.
- D. The MRP run plans the material only if a quotation has been maintained.
Answer: C
NEW QUESTION # 26
Which of the following are features of the clean core dashboard?
Note: There are 2 correct answers to this question.
- A. Customers can use the dashboard in the dev test production tenants.
- B. Customers can grant access to the dashboard to partners.
- C. It can be accessed by using SAP For Me.
- D. It can be used in all SAP S/4HANA Cloud editions.
Answer: B,C
NEW QUESTION # 27
What are some SAP recommended guiding principles to achieve clean core operations?
Note: There are 3 correct answers to this question.
- A. Establish release management.
- B. Establish an organizational structure technical foundation transformation methodology for clean core.
- C. Integrate clean core practices in the endtoend value process chain.
- D. Define roles responsibilities as part of a process transformation office.
- E. Establish regular housekeeping tasks procedures.
Answer: A,B,D
NEW QUESTION # 28
Which alternative item strategies are available in bills of material (BOMs) in SAP S/4HANA Cloud Private Edition?
Note: There are 2 correct answers to this question.
- A. First in first out (FIFO)
- B. Manual maintenance
- C. Simultaneous
- D. 100% check
Answer: B,D
NEW QUESTION # 29
In documentation for MRP in Advanced Planning you read that new orders are created through infinite planning.
What does this mean for the capacity requirements of a new order?
- A. MRP assigns the capacity requirements automatically to work centers with the earliest available capacity.
- B. MRP creates the capacity requirements at the earliest possible time.
- C. MRP creates the capacity requirements without considering existing load on the work centers.
- D. MRP assigns the capacity requirements automatically after the last scheduled operation for each work center.
Answer: D
NEW QUESTION # 30
Advanced Planning is delivered with standard out-of-the-box order and resource evaluations.
Which evaluations are available?
There are 2 correct answers to this question.
- A. Resource utilization
- B. Order list
- C. Production list
- D. Resource overview
Answer: A,B
NEW QUESTION # 31
You are a consultant on an SAP S/4HANA Cloud Greenfield project.
Which of the following aspects should you focus on to achieve maintain clean core data quality?
Note: There are 2 correct answers to this question.
- A. Stability
- B. Accuracy
- C. Timeliness
- D. Efficiency
Answer: A,D
NEW QUESTION # 32
Advanced Planning uses master data from SAP S/4HANA Cloud Private Edition.
In which data objects can you set the Advanced Planning flag?
Note: There are 2 correct answers to this question.
- A. Production version
- B. Work center
- C. Material
- D. Plant
Answer: B,C
NEW QUESTION # 33
What are the prerequisites for a reporting point confirmation in repetitive manufacturing?
Note: There are 2 correct answers to this question.
- A. Activating the reporting point backflush in the order dependent parameters
- B. Defining the operations as reporting points using the control key
- C. Activating the reporting point backflush in the work centers
- D. Defining the relevant work centers in the routing
Answer: B,C
NEW QUESTION # 34
Why would you use phantom assemblies?
Note: There are 3 correct answers to this question.
- A. To make the assignment of components easier
- B. To simplify the structure of bills of material
- C. To reduce the number of changes required in bills of material
- D. To increase the number of planning levels
- E. To reduce the number of material masters
Answer: A,B,C
NEW QUESTION # 35
Which of the following automation options can you use for production orders?
Note: There are 2 correct answers to this question.
- A. You can use mass processing to read PP master data for production orders.
- B. You can use the production scheduling profile to automatically set orders to technically complete.
- C. You can use mass processing to set production orders to technically complete.
- D. You can use trigger points to automatically create rework orders via confirmations.
Answer: C,D
NEW QUESTION # 36
What options does a planner have in the planning table for repetitive manufacturing?
Note: There are 2 correct answers to this question.
- A. Create new production quantities.
- B. Reschedule deallocate operations.
- C. Dispatch operations to work centers.
- D. Change the assignments of production quantities to production lines.
Answer: B,D
NEW QUESTION # 37
You are trying to create a production order NO valid production version can be selected.
What could be the reasons?
Note: There are 2 correct answers to this question.
- A. All production versions for the material are locked.
- B. The order lot size is NOT within the validity range of a production version.
- C. NO bills of material (BOMs) are assigned to the production versions.
- D. NO production lines are assigned to the production versions.
Answer: A,B
NEW QUESTION # 38
......
Real SAP C-TS422-2601 Exam Questions [Updated 2026]: https://pass4sure.actual4dump.com/SAP/C-TS422-2601-actualtests-dumps.html